500 cubic meter Concrete Ground Reservoir

Completed last August 7, 2014, the 500m3 concrete ground reservoir with booster pumphouse is GSCWD’s measure to address the call for increased water supply and enhanced service to its concessionaires in Calumpang and Fatima service coverage areas

p.5

This water storage, built within the premise of Pumping Station No. 12, Zone 11-A, Brgy. Fatima, General Santos City, amounted to P4,250,029.90 which was contracted last September 1, 2013.

This new construction will augment water supply during peak demand hours especially to elevated areas in the said barangays.